• Total Project Budget: $5,050,000
  • Funding source(s): $4,400,000 mix of taxable and non-taxable bonds  + $500,000 UHDS major projects funds; $150,000 UHDS FY16 minor capital projects
  • Construction Begin Date: Fall-15
  • Projected Move In Date: Summer-16
  • Description of programs and benefits to OSU: The SCC project will provide a new child care facility, offices for Child and Family Resources, program and office space for the Human Service Resource Center (including a food pantry, demonstration kitchen, and community lounge/meeting space), and office space for UHDS Administrative offices to be moved from Buxton Hall (this is in addition to renovated space in Oxford house for UHDS admin offices)
  • New Building or renovation of old: renovation of old, site improvements to alley and off-alley parking area
  • Architect: Hennebery Eddy Architects
  • General Contractor: Howard S. Wright
  • Square Footage: Azalea House:  11,938 gross sq. ft.; Avery Lodge: 12,507 gross sq. ft.