• Total Project Budget: $42,000,000
  • Funding source(s): Gifts $42,000,000
  • Construction Begin Date: Fall-15
  • Projected Move In Date: prior to the first Football Game of 2016
  • Description of programs and benefits to OSU: Addition of 55,000 SF to benefit student athletes, the football program and all OSU athletics programs which serve more than 500 student athletes participating in 17 sports.   The renovation and addition will include a new home team locker room, football program meeting spaces, expanded sports medicine facilities, expanded equipment area, renovated north end zone seating with a direct connection to the east stands and a new building entrance.
  • New Building or renovation of old: Addition and Renovation
  • Architect: HNTB Corporation
  • General Contractor: Hunt Construction Group
  • Square Footage: 55,000