Work in Burt Hall II included replacement of research facilities and offices damaged by smoke, water, or heat from the fire that occurred November 30, 2018. Burt Hall II was upgraded to modern building code, including ADA improvements. Capital Planning and Development, CEAOS, Insurance & Risk Management Services, PCMM, a project manager from College of Business, and business centers have worked collaboratively since the fire to ensure that the insurance claims are submitted, that the space is renovated, and that research operations resume.
Last Updated:
Wednesday, October 6, 2021
Project Details
Project Status:
Complete
Project Category:
Capital renewal project (deferred maintenance)
Completion Date:
September 2020
Project Budget:
$10.5 Million
Funding Source(s):
Insurance reimbursement and OSU Capital Improvement and Renewal funds
Type of Project:
Other
Project People
Project Manager:
Dustin Sievers
Architect:
YGH Architecture