Expansion of the veterinary hospital and teaching facilities at Magruder Hall. Additional 6,600 sq. ft. for exam rooms, kennels, wards and new linear accelerator in oncology.
The lecture hall will have the storm drain going in this week. Inside the lecture hall the flooring will be installed, as well as the vestibule installation. The clinic’s activities will be carrying on from last week, the window frames will be installed, with the 2nd floor drywall and overall flooring in the building. Also, …
Most work from last week at the clinic will be continuing through this week, the storefront windows and glass glazing will be installed and the 2nd floor framing and sheetrock will also continue. New at the clinic this week, the new resilient flooring will start to go in. The lecture hall also has several activities …
At the Clinic, the metal panels at the connector will be installed. As well as, the windows and those glass glazing throughout the clinic and the cabinetry will also be getting installed this week. The second floor of the clinic will also see sheetrock and framing and the mechanical, electrical and plumbing rough-ins. The lobby …
This Saturday, July 20th, Magruder Hall will have both water and electricity shutdown from 6am-4pm. This shutdown is in conjunction with tying in new waterlines for the clinic, lecture hall and LINAC. During this time, Pacific Power will shutdown electricity so they can perform work to tie new electrical services into the existing transformer. The …