Primary construction activities for the week of 05/25 thru 05/29 will consist of the following: | * = Activity delayed | ROOFING Install Tsunami Signs: No Activities this Upcoming Week. INTERIOR BUILDOUT Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace: Fireplace Install and Grout Begin Third Coat Delay* Finish Installing Wood Ceiling*… Continue reading →
Primary construction activities for the week of 05/15 thru 05/22 will consist of the following: | * = Activity delayed | ROOFING Install Tsunami Signs: No Activities this Upcoming Week. INTERIOR BUILDOUT Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace: Install Base* Fireplace Install and Grout Paint Conduit and Hangers for Wood… Continue reading →
Primary construction activities for the week of 05/11 thru 05/15 will consist of the following: | * = Activity delayed | ROOFING Install Tsunami Signs: No Activities this Upcoming Week. INTERIOR BUILDOUT Lab Wing – Level 1 – Commons Spaces, Café, & Fireplace: Install Wood Ceiling and Lighting Install Base* Begin Third Coat Delay Common… Continue reading →